Currently, there is rental revenues which include long term leases, hall rentals, and commercial kitchen use
We have done fundraising for on-going repairs and maintenance
We had to replace the boiler ($32, 075)
Repair plumbing and update electric including wiring and lighting
In phase one, the SCCH spent $128, 361
This is architectural and engineering costs
This number is higher than expected due to delays in obtaining permits
Removing existing partition for new opening
Existing doors and frame to be removed, and provide 1 hour rated partition, & 20 minute rated doors and frame
New shop fabricated wood stairs to stage, provide oak treads and risers, pine treads
New doors and wall to ceiling: 1 hour fire rated partition, 20 minute doors, ¾ hour rates transom
Replace existing door, with existing frame to remain
Existing stairs to remain. Provide new wood hand railing both sides
New drinking fountain: Halsey Taylor Cooler, wall mount, bi-level, Ada vandal resistant, filtered, non-refrigerated, stainless, HVR-BL-WF-LR. See elevation
Existing cooler by owner, relocated by G.C. Typ. of 4
Replace existing doors, jambs, and hardware, electric remote operation
Remove existing canopy and replace with new entry canopy, see exterior elevation, drawing 5/A3
New interior partitions: 5 ½ Stl. Studs at 16’’O.C. -5/6 Gypsum board each side. Provide acoustical insulation where shown on plan
Furr existing wall: 31/2’’ STL. Studs at 16’’O.C. and 5/6 Gypsum board.
Use water resistant board at bathroom and behind drinking fountain
Acoustical insulation BATTS. Seal all penetrations to ceiling and floor
Existing wall to remain
Replace transom in window with maple solid panel
Existing ramp and railing to remain. Add steel pipe railing against wall
Existing stairs and railing to remain
Remove existing partition and patch walls
Remove existing door and frame. Infill partition to match existing. Provide 1 hour fire rated construction
Remove existing partition for new door and frame
Relocate fire alarm for new doors and frames
New toilet partitions. Remove and dispose of existing partitions
Remove and replace all existing plumbing fixtures
New ceramic tile and gypsum board wall finish this room.
Remove front covering of stage. Repair structure. Provide wood paneling to match walls. Review structural conditions for potential repairs before replacement.
Add railing to match existing
Accessory occupancy
Remove existing enclosure patch adjacent surfaces
Platform wheelchair lift in unfolded position at base
Platform wheelchair lift at top of run
Platform wheelchair lift rail per manufacture